Wednesday, March 28, 2012

Door to the Thrown Room

The head and shower area on Moor or Less is not what you would call over sized. Providing easier access the door to the head is a bi-fold door, with piano hinges used to secure the two halves of the door together as well as attaching the door to the door-jam.

The problem with the installation is that the piano hinges that were used were not stainless steel, resulting in two issues.  The first issue is that in the marine environment, the piano hinges have corroded and seized. The second issue is the mess that corroding hinges leave on the floor of the head (piles of rust dust).

Hinge Replacement
The hinges would need to be replaced with stainless steel hinges. Using a Phillips head screw driver, I removed the 20 odd small screws attaching the door to the door-jam, to take back home to work on it. Once home, the two parts of the door were separated with the removal of the second corroded piano hinge.

Instead of using piano hinges I decided to replace the piano hinges with 4 x 25mm stainless steel butt hinges, both for the joining of the two halves of the door, and to attach to the door itself to the jam. After measuring out the locations of the hinges, I marked where the timber will need to be removed for the recess, and where the holes drilled for the screws.

Drilling 2mm pilot holes in the edge of the door for the screws was to prevent the timber splitting, as the door was only 20mm thick. Next came the chiseling of the timber, which was quite easy with my newly purchased and, and very sharp chisel. To secure the hinges to each door edge I used 3 x 20mm x 6 g stainless screws in each hinge.

The two door halves were quite stiff even though they were only 20mm thick. The alignment of the hinges with each other is important to ensure that the door isn't stressed when being opened, which may result in the splitting of the timber.  A trick when installing small cabinet hinges is to fully open the hinge so that sits flat against the face of the door, and clamp it while tightening the screws.

Once all the hinges were installed on the door, it was ready for re-installation onto the boat.

Door Latch
There had never been a door latch installed on the door, and one would be needed when guests are onboard. The bi-fold door would fold back on itself, so the selected latch would need to be thin, else hit against the other half of the door.

Another challenge was to make sure that the portion of the latch which mounted on the door-jam didn't protrude too much, as it would catch on peoples clothing when entering/leaving the head. The alternate method was to install a low profile latch onto the door-jam, and mount the striker plate onto the edge of the door. This appeared to be a better option, so a low profile stainless steel toilet door latch was purchased, similar to those seen on public toilets with the indicator panel to show if it was vacant or occupied.

Tuesday, March 27, 2012

Installation of the Deck Fittings

Layout
As the vessel had never been finished, one area which was outstanding (one of many) was the deck fittings. The vessel had only the hatches installed and a few bollards for attaching mooring lines. This means that all the sailing hardware had to be decided upon, purchased and then installed.


Winch Selection
There are several winch manufacturers to select from, but having used ARCO winches on my previous boats, and never had any problems with these beautifully engineered winches. The winch manufacturer selection process was easy.

The ARCO winches are also covered by a lifetime warrantee. A company with that much confidence in their product wins me over.

The next step was how many, where, and what type and size. Being a cruising vessel, I was determined to have a sail and rigging plan which was as straight forward as possible.  A simplified sail plan will reduce the number of control lines, clutches and general clutter in and around the cockpit.

Self-tailing winches on the headsail sheets was a must, with two speed gearing of suitable ratio to enable a small statue person handle the full headsail. After looking at several similar size boats, I decided on decided on the ARCO 40 two speed self tailing winches.  This size/type selection also lined up with that suggested size on the ARCO website.

To assist with short-handed sailing, having all the control lines coming into the cockpit area will mean that reefing and adjusting sails ccan be done without leaving the cockpit.
Two coach house winches will be needed for the sail control lines (reefing lines, outhaul, halyards, topping lift).

Self-tailing winches would free up a hand, which always seems a bonus when adjusting sails.

The coach house on either side of the companionway is not very wide. On an older 31 foot boat, the width of the cockpit is typically not exceptionally wide.  With a dodger in place, the winch handle in a coach house mounted winch would not be able to complete a full circle.  Using single speed winches would mean that the handle could be rotated backwards without load.  The ARCO 30 single speed self tailing winches were selected as a balance between speed and mechanical advantage.


Rigging
The mast which came with the vessel was originally a mast from a racing Cole 31. The mast utilises wire/rope halyards, which I dislike with passion (having sliced hands open on several boats which had wire halyards in the past).

The wire/rope halyards will be replaced with 8mm Spectra rope. Using the Spectra means that I can still use the same exit slots in the mast (just replace the blocks), but more importantly, it will be possible to use standard rope winches/clutches/deck organizers.

The headsail will be on a furling system, and as it will be on the furler for the majority of time, will be cleated off at the mast.  The main and MPS halyards will be returned to the cockpit, as will the two mainsail reefing lines, out haul, and spinnaker pole topping lift.  This means a total of 6 control lines need to be returned to the coach house winches, 3 lines per side.


Rope Clutches & Deck Organizers
Triple Rutersgen rope clutches, (one on each side) will be placed in front of the coach house winches for the sail control lines. Between the mast and the rope clutches, the control lines will need to turn through an angle of approx 70 degrees after exiting the mast base. These deck mounted blocks are often called deck organizers, and will also be from the Rutersgen line of products.


Headsail Tracks & Cars
Again Rutersgen was selected for the headsail tracks and cars. Most of the Adams 31 CCs looked at have 3m sections of tracks, however only the back 1m section apprears to have ever been used. The headsail will be on a furler resulting in the foot and clew being high off the deck, it is pointless to carry the track forward of the mast even at 50% sail, so 2m sections were selected.

Storm sails should always have the sheets attached. Separate anchore points and blocks will be used for the storm jib.


Installation Begins
Once you have the fittings, there becomes an eagerness to install. A boat without deck hardware looks very bare, so as soon as possible the bits and pieces would be installed.

Many of the bolts fastening the deck hardware would be coming into the main saloon area, dome nuts would be needed. The dome nuts not only make them appear more presentable, but also safer (no sharp threads left exposed). Once the locations for the winches were determined and marked out, the holes were drilled, bolt lengths measured, and the appropriate fastenings purchased.

First winch base mounted on Starboard side


On my previous boats, I have had varying degrees of success with Sika-flex and silicon based sealants. After speaking with several shipwrights, I am convinced that the Selleys' Mastic is a better option, as it will re-seal if there is any movement.

The winches were the first to be installed, starting with the headsail sheet winches. The winches were mounted in the middle of the cockpit coaming to allow for the sheet to be fed from either forward or aft. Placing them in the centre also allows the helmsman to reach them by just reaching around from behind the wheel.  This will be good for single handed tacking.

Placing ample sealant around each of the holes, and coating the bolt threads before inserting them through the holes will hopefully provide a good seal. The port winch was a one person job, as I could reach and turn the nuts on the bottom through the lazarette while at the same time hold the bolt heads from the top. With the starboard winch however I needed the assistance of another pair of hands.

Mounting the fittings on the coach house, either side of the companionway, it was possible to reach both the bolt heads and nuts at the same time, making the installation a one person job.  The rope clutches for the sail control lines were installed quickly thanks to their design. The design provides for the base of clutch to be detached for mounting onto the surface.  This design has the added benefit of allowing the rope clutch to be maintained in the future, without disrupting the sealant.

Bench Top Creation

After having worked out what I wanted in the layout of the saloon, it was time to get started.  Continuously looking at the design doesn't make it happen.
Firstly the table would need a support frame which will be attached to the cupboard under the table, and the mast compression post.
I wanted the support frame to be made of Stainless Steel, so would need an engineering shop to make it up for me. I put created a detailed drawing of what I was after and took it to an engineering factory near where I was living in Wanchai (HK). To give me confidence in my drawing, the guy in the factory seemed to understand what I wanted.....  "seemed to" because he didn't speak English, and I can't speak Cantonese.
We agreed on a price, and I left 50% deposit, wrote my contact number on the drawing, walking away happy. While it was only a small job, I still expected it to take about 2 weeks, to my surprise the frame was ready two days later, and was exactly what I wanted.
Now with Confidence from the support frame experience, it was time to tackle getting the bench tops made.
The Plan
Step 1: Make full size paper patterns of the bench tops in the boat to make sure that the design works. (at least layout wise).
Step 2: Make detailed drawings from the paper patterns (these took me soooo long to do).
Step 3: Take the drawings to the kitchen place to get quotation and place order.
Step 4: Sit back and relax, it was going to take a couple of weeks for them to make it.

What Happened
Step 1 & 2 all went ahead as expected, however at Step 3 things changed. I presented the drawings to the sales assistant in the kitchen bench top shop in Wanchai (you can get everything, and I mean everything, in Wanchai), he asked me to select the colour I would like from the samples while he worked out a price. We had a similar language challenges as in the engineering place, but we could communicate ok, it adds to the fun of shopping. Shopping is not something I enjoy doing back home in Sydney, however in Hong Kong, it is fun.
He came back with price, this is where I could use the “standard phase” in Cantonese when haggling over price.  The phrase is "Wha!" (it is a general purpose phase, however in this situation it roughly translates to "holy crap"). He responded with "ok ok" (I understood that part), and immediately dropped the price by 25%, while I thought the price was reasonable, I thought I would try and lower it further with the "old walk away trick"........ it didn't work. I had to repeat the exercise in the shop two doors down.  This time I got a better price from the start, but still did the "Wha!"  (part of the fun), and got a further drop in price. We agreed on the price and the order was placed, again with 50% deposit.
The order was again ready before I expected, only 4 days.  I wanted it delivered to the office, where it could be stored until taken back to Sydney, where the boat is located. I received a phone call, saying that they would deliver it that morning. It would be at 11am and for me to meet them outside the building (silver van). I was on time, but no sign of them, the driver then rang me directly, and with broken English/Cantonese told me he was here, where was I...  I was in front of the building, couldn't see him. I went to solicit help from the security guard at the entrance to the loading bay of the building so he could talk to the driver. The challenge was the guard didn't speak English either.... no worries, I called hte drivers number and simply handed over the phone to the security guard. The driver was already waiting at the loading dock, problem solved.

Gally benchtop, sallon table, and drop leaf on office floor
I got out my paper patterns and laid them over the top of the finished bench tops, they were perfect.  Language barriers are easily solved with pictures, hand gestures, and smiles.
The two main reasons for getting them made in Hong Kong was, firstly convenience (living in HK), and secondly was price.  It is significantly cheaper to have things made in Hong Kong than in Sydney. It never ceases to amaze me that both processed food and fresh vegetables from Australia are much cheaper in Hong Kong than they are in Sydney. I had solid surface bench top made 20 years ago on a previous boat, and that was more than three times the price I had just paid.
Getting the bench tops and frames back to the boat would be done over time, each trip I would box up and item, and take it as check-in baggage.  Doing it over several trips was not due to hitting weight limits (I have a 46kg allowance), but the challenge is handling the boxes at the airport. As I make regular trips, it wasn't too much of a problem spreading it out.